Cell 4 has been filled to 6 inches below marsh level with a delta around the outfall at -4 inches.

We dredged December 13-14, but holiday activities have delayed the report. I hope to have it completed before the end of the year.

Cell 5 is full and sitting fallow, and Cell 4 has been filled up to 6 inches below marsh level with fluid mud and has formed a delta of heavier material around the outfall at around -4″. A good bit of material was observed on the bottom of the remaining 3 cells when I paddled around the pond.

We are planning to upgrade the dredge now that we have the experience to recognize where the efficiency could improve, so the new year should show increased productivity.