Dredge (and Rainey) Report Cell 5 to Marsh Level November 4, 2011

November 4, 2011

Summary of accomplishments:

  • Dredging into Cell 5; substrate at +1 inch ML
  • Repaired containment 5a, 5b; added containment 4a
  • Total cumulative time dredging in Cell 5 (with spillover to Cell 4 & 3): 65 hours
  • Total dredging time at study cells: 83 hours
  • Impediments: low water level; very windy

 