April 24, 2013 – No dredging – Marshbird Surveys

Dredge and Rainey Report No dredging – Marshbird Surveys April 24, 2013 Summary: Low water patterns dominate, discouraging dredging. The dredge is at the limit of the hose length in the canal, and any dredging would require moving hoses and … Continue reading

Posted in Marshbird Survey, The Paul J. Rainey Wildlife Sanctuary | Tagged , , , | Leave a comment

April 11, 2013 – High Water Dredging in C3

Dredge and Rainey Report High Water Dredging in C3 April 11, 2013 Summary of accomplishments: Total time dredging this week into Cell 3: 10.75 hours Total time dredging into Cell 3: 75 hours Total time at experimental site: 221.5 hours … Continue reading

Posted in Dredge Reports, Marsh Restoration, The Paul J. Rainey Wildlife Sanctuary | Tagged , , , , , , , | Leave a comment