Daily Archives: May 25, 2012

Week ending May 25, 2012 – LSU review of site

Dredge (and Rainey) Report LSU review of site May 25, 2012   Summary of accomplishments: Cell 4 full – settled to +1 throughout and covered with mudcracks Total time pumped directly into Cell 4 (0.352 acres) = 72 hours Total … Continue reading

Posted in Dredge Reports, Past Week Summary | Comments Off on Week ending May 25, 2012 – LSU review of site

May 21, 2012 – rain and marsh fires

Monday, May 21       I made it out to the Rainey headquarters at 3:00 on a bright and sunny afternoon. I unpacked and walked over to watch the camp construction.     Within 2 hours, the sky darkened, … Continue reading

Posted in Dredge Reports | 1 Comment

May 22, 2012 – plant terraces, marshbird survey

Tuesday, May 22   Dawn was clear, promising a hot steamy day after last night’s storm. The Christian Marsh grass planting had marsh grass leftover that the volunteers had not had time to plant last week, and Timmy didn’t want … Continue reading

Posted in Dredge Reports, Marsh Restoration, The Paul J. Rainey Wildlife Sanctuary | Comments Off on May 22, 2012 – plant terraces, marshbird survey

May 23, 2012 – marsh bird survey, Cell 4 & 5 mud cracks

Wednesday, May 23  The morning marshbird survey starts early, 30 minutes before sunrise, which meant Erik Johnson and I were in the boat and at the first survey point by 5:30. The sun didn’t come up until our second point. … Continue reading

Posted in Dredge Reports | Comments Off on May 23, 2012 – marsh bird survey, Cell 4 & 5 mud cracks

May 24, 2012 – LSU visit

Thursday, May 24 One more marshbird survey this morning, from 5:15am to 9:30, and I took Erik back to the landing so he could head home. LSU was there and Timmy with the big boat, the Goose, was already loaded … Continue reading

Posted in Dredge Reports, Marsh Restoration, The Paul J. Rainey Wildlife Sanctuary | Comments Off on May 24, 2012 – LSU visit